Station Construction Updates as of 1/2/2022

CDOT Camera @ HARTSEL…click on left arrow to view our station (right side of view)

 

Design and project supervision: Davis Partnership Architects

HARTSEL STATION PROGRESS

Hartsel Project General Contractor: MW Golden Constructors.

January 2, 2021

Finalizing some interior work and preparing for final electrical inspection.

Ambulance test fit. Looking good.

October 25, 2021

Covid has impacted construction time-frame. Getting close to opening. On budget.

 

MICHIGAN CREEK STATION

January 2022

Site work has begun on the site located at MM 195.5 on US 285 (between Jefferson & Como).

July 12, 2021

Final construction documents for this project completed and being submitted for building permits. Work on site access to begin soon.

May 27,2021

We own the property. Wildlife-friendly fencing will be installed soon.  The area is home to large herds of antelope and elk. After fencing is completed the highway access will be constructed.

May 11, 2021

Closing on the property 5/26/21. Thank you to Paul & Lorri McDaniel for the generous donation of 3 acres of their ranch. Until they graciously stepped forward, we were at a dead-end in finding suitable property.

Soil testing completed for the civil engineer team and septic design. Site is located on the east side of US285 at MM195.5. Construction to begin mid- June with construction of highway access driveway.

April 21, 2021: We are pleased to announce that we will continue working with MW Golden Constructors for the construction of our Jefferson area station.

Sub-Contractors interested in submitting proposals use this link ->->->  

Request For Proposal Closed / April 16, 2021

South Park Ambulance District will announce bid award on April 21, 2021.

This is the second of two prototype designed stations to be constructed. Please use the following links:

  1. Request For Proposal
  2. Prototype Construction Documents
  3. Legal Notice